New to this? Read it in simple words
  • Oracle is building a huge AI data centre in New Mexico for the Stargate project.
  • It sent a legal notice that could let it delay payments if the site opens late.
  • The site has had problems with its power supply and its permits.
  • Oracle says the project is still on schedule.
Words to know
Force majeure
A contract rule for events outside a company’s control, such as disasters or long delays.
Data centre
A building full of computers that run online services and AI.
Permit
Official permission needed to build or run something.

Project Jupiter is a giant AI data-centre campus planned in New Mexico. On September 24, Bloomberg reported that Oracle had sent a force majeure notice about it. Oracle says the campus is on track, and its developer says nothing has changed financially.

What the notice does

Oracle sent the notice to Blue Owl Capital, which owns Stack Infrastructure, the developer of Project Jupiter.

Force majeure is a contract term for events outside a company’s control. According to reports based on Bloomberg’s story, the notice could let Oracle put off payments if the campus does not open in 2028 as planned.

Reuters, citing a person familiar with the matter, reported that the notice would stretch out a period of lower rent during construction. Oracle cannot end the lease, the source said.

Sources124

Check
A legal safety net, not yet a delay.

Oracle says the campus remains on schedule. The notice covers a possible late start.

Power and permit problems

Project Jupiter is a 1,400-acre campus in Santa Teresa, in southern New Mexico. Reuters describes it as part of Stargate, the data-centre effort with OpenAI and SoftBank.

According to the Albuquerque Journal, the site is planned with a 2.45-gigawatt power plant. The Santa Fe New Mexican reports that a gas pipeline meant to power it has not yet been approved by the New Mexico State Land Office.

The campus also faced legal fights over air-quality and water permits. On September 17, the New Mexico Supreme Court allowed those permit proceedings to continue.

About $18 billion in loans are tied to the project. The Santa Fe New Mexican, citing the Financial Times, says those loans are being quoted at 89 to 91 cents on the dollar.

Sources234

What the companies say

“Force-majeure notices are commonplace in developments of this scale,” said Oracle’s Michael Egbert. “They do not, by themselves, establish a project delay or change delivery expectations.”

Oracle says Project Jupiter “remains on our planned schedule”.

“Blue Owl, STACK Infrastructure and Oracle remain fully aligned on Project Jupiter,” said Stack spokesperson Nikki Wheeler. The notice “does not change the financial commitments to this multiyear project”, Wheeler added.

Oracle’s shares closed about 3.5% lower on Thursday, and Blue Owl’s fell 3.6%, the Santa Fe New Mexican reported. OpenAI did not comment in the reports we read.

Sources234

Sources

Every fact in this story comes from the sources below. Open them to check our work.

  1. 1
    Primary source · September 24, 2026Oracle Cites ‘Force Majeure’ to Shield Itself on Controversial Data Center Bloomberg via Yahoo Finance
  2. 2
  3. 3
  4. 4
How we checked this story

Bloomberg broke the story; other reports confirm the main facts and carry the quotes. Reports differ on the size of the Stargate deal, so we leave that figure out.

Oracle sent a force majeure notice on a Stargate campus. Silicon AI News, September 25, 2026. https://siliconainews.com/stories/oracle-project-jupiter-force-majeure

More on this story

Mood: 4.1 out of 10 · Slightly negative

Oracle sent a notice that could delay payments on a huge data-centre project with power and permit problems, though it says the schedule holds. How we rate the mood

The mood shows how the news frames the event for the tech and AI world: as an opportunity (6 and above) or as a loss (below 5). It is not our verdict on who is right.

Basics explainedWhat happens when you use an AI model?
Your next step · Claim CheckIs it hype or happening?